The Emerald Trail in Jacksonville, Florida

A planned 30-mile ring of trails, greenways and creek parks around downtown Jacksonville, opened with the 1.3-mile LaVilla Link on May 6, 2024.


Short answer: The Emerald Trail is a planned 30-mile bicycle and pedestrian trail and linear park system that will connect 14 historic neighborhoods and downtown Jacksonville, according to the Jacksonville Transportation Authority. Groundwork Jacksonville is developing it with the City and JTA, with $132 million from the Local Option Gas Tax. The 1.3-mile LaVilla Link opened on May 6, 2024, and the Hogan Street Link broke ground in fall 2025.

Last verified: October 18, 2026, against the sources listed at the end of this page.

What is the Emerald Trail?

The Emerald Trail is a planned 30-mile bicycle and pedestrian trail and linear park system around Jacksonville's urban core, being developed by Groundwork Jacksonville with the City of Jacksonville and JTA.

The Jacksonville Transportation Authority describes the trail as a system that will connect 14 historic neighborhoods and downtown Jacksonville to local and regional trails, parks, schools, businesses, transit and other destinations. JTA lists it under City Council Districts 5, 7, 8, 9 and 14, with an estimated cost of $132,000,000 and a project status of design.

Groundwork Jacksonville, the nonprofit planning the system, says that when complete it will encompass more than 30 miles of trails, greenways and parks that encircle the urban core and link at least 14 historic neighborhoods to downtown, Hogans Creek, McCoys Creek and the St. Johns River. Its current page counts 16 schools, three colleges, three hospitals, 21 parks and the Regional Transportation Center along the route, with 13 additional schools and 17 parks within three blocks. The October 2023 JTA and Groundwork release gives the same counts except two colleges rather than three, so the two published figures differ on that one item.

Where did the Emerald Trail plan come from?

The current route comes from the Emerald Trail Master Plan, which the Jacksonville City Council adopted on March 26, 2019, according to JTA.

Groundwork Jacksonville says its master plan was developed by the PATH Foundation, which it describes as having built more than 260 miles of trails throughout Georgia, together with landscape architect KAIZEN Collaborative. The Groundwork Emerald Trail page states that the $88,200 plan cost was privately underwritten by a $50,000 donation from JTC Running, with grants from the Local Initiatives Support Corporation and the Giving Forward Community Endowment Fund at The Community Foundation for Northeast Florida. The plan divides the work into Programmed Segments, Implementation Tier 1 and Implementation Tier 2, with the stated goal of always having a segment in acquisition, design, permitting or construction.

At the 2021 groundbreaking, Groundwork CEO Kay Ehas called the trail a collective vision for almost a century and one of the primary goals for establishing a Groundwork Trust in Jacksonville, according to Groundwork. The same release described the 30-mile Emerald Trail as a public-private partnership between the City and Groundwork and projected completion by 2029, a date later superseded by the federal grant schedule described below.

Which part of the Emerald Trail is open?

The 1.3-mile LaVilla Link, the first segment, opened on May 6, 2024, with a ribbon cutting hosted by Mayor Donna Deegan, Groundwork and Baptist Health, Groundwork reports.

Groundwork records that Mayor Lenny Curry and Groundwork broke ground on the LaVilla Link on August 24, 2021, with an estimated construction cost of $8.9 million. The 14-foot-wide concrete pedestrian and bicycle trail runs from Park and Stonewall streets in Brooklyn over the Park Street Bridge, north along Lee Street, west at Church Street and across Beaver Street to the S-Line Rail Trail at Wilcox Street and State Street in the Railyard District. Groundwork credits the design to Pond and construction to Astra Group, and lists privately funded features: the Park Street bridge overlook, the Lee Street Pond boardwalk and overlook, and a butterfly garden along West Church Street just east of I-95.

In its opening announcement, Groundwork says the LaVilla Link was designed and constructed by the City in partnership with Groundwork and funded by the City and charitable support, with Baptist Health as lead investor. The link was not in the first plan draft; Durkeeville and New Town residents suggested it for direct access downtown, according to Ehas. It connects the Prime F. Osborn Convention Center, the Regional Transportation Center, the Beaver Street Enterprise Center and the existing S-Line Rail Trail, creating nearly three miles of contiguous trail, and it serves as the trail's Model Project.

What is under construction and planned next?

The Hogan Street Link through downtown Jacksonville broke ground in fall 2025, with construction continuing through 2026, according to JTA.

Groundwork describes the Hogan Street Link as a 0.9-mile trail linking the St. Johns River to FSCJ and Springfield through the urban core, with a first construction phase from Water Street to Union Street. Points of interest it lists along the way include Riverfront Plaza, James Weldon Johnson Park, the St. James Building (City Hall), the Museum of Contemporary Art, the Federal Courthouse, the Jacksonville Public Library and the JTA Rosa Parks Transit Station.

The Riverside Link is a 2.3-mile segment that will connect Riverside to North Riverside and McCoys Creek and tie into the Florida Department of Transportation shared-use path across the Fuller Warren Bridge to the Southbank Riverwalk and San Marco. Groundwork names HDR and SCAPE Landscape Architecture as design partners and calls a $1 million grant from the Delores Barr Weaver Legacy Funds and the J. Wayne Weaver Fund at The Community Foundation for Northeast Florida its largest single private donation; the James M. Cox Foundation added $500,000 for design. Its page, written before 2026, said design would continue through 2025 with construction expected to begin in 2026. A spur along Riverside Avenue is planned to connect the Artist Walk at the Northbank Riverwalk to Memorial Park.

The creeks are part of the same program. Groundwork lists a February 5, 2026 groundbreaking with the City on the McCoys Creek Branches restoration on its LaVilla Link news page. Its Hogans Creek page describes a 2.6-mile tidal and freshwater creek that begins at the CSX Railroad just north of the S-Line Rail Trail and flows south to the St. Johns River at the Shipyards, flooding Klutho and Springfield parks in moderate rain; the restoration design is at 60 percent and would restore 1,300 feet of daylighted creek. Residents asked that the historic park features designed by Henry Klutho, including the balustrades, be protected.

How is the Emerald Trail paid for, and what happened to the federal grant?

The base funding is $132 million from Jacksonville's Local Option Gas Tax, while a $147 million federal grant awarded in 2024 was rescinded in July 2025.

On October 26, 2023, the City, Groundwork and JTA announced a Memorandum of Understanding for the five remaining trail segments, to be funded in part by $132M from the Local Option Gas Tax. Under it, Groundwork leads outreach and trail design, JTA leads permitting and construction procurement, and the two jointly negotiate with designers. The release put 40 percent of the trail complete, under construction or in design at that time, and noted that JTA and Groundwork had submitted a $184M Neighborhood Access and Equity grant application to the U.S. Department of Transportation in September 2023.

On March 13, 2024, JTA announced that the City, JTA and Groundwork had been awarded a federal grant of $147 million to design and construct the five segments, the largest one-time federal grant the City of Jacksonville has ever received and one of 132 awards announced by USDOT that day. In a July 9, 2025 letter, Groundwork said it had been informed that unobligated grants under the Federal Highway Administration Neighborhood Access and Equity Program were permanently rescinded, including the $147M Emerald Trail grant. Groundwork wrote that work would move forward on segment 3 in Riverside and segment 4, the S-Line Connector, because both are partly funded by the gas tax and private donors, that completion under the grant had been anticipated in 2031, and that the grant had included more than $3.5M for Groundwork's own project management and community engagement.

The five remaining Emerald Trail segments (JTA, March 13, 2024)
SegmentNameConnects
3SouthwestRiverside to McCoys Creek
4S-Line ConnectorLinks to the S-Line Rail Trail
6WestsideNorth Riverside, Woodstock and Robinsons' Addition
7NorthwestDurkeeville, College Gardens and New Town
8EastsidePhoenix and Springfield

Groundwork's letter puts those five segments at roughly 15 miles of trail, and its Emerald Trail page map now shows half of the 30-mile Emerald Trail in design, under construction or complete. Last verified: October 18, 2026, against JTA's Emerald Trail project page and its 2023 and 2024 releases, plus Groundwork Jacksonville's own project pages and its July 2025 grant letter.

Frequently asked questions

How long is the Emerald Trail?

JTA describes the Emerald Trail as a 30-mile bicycle and pedestrian trail and linear park system, and Groundwork Jacksonville says the finished network will encompass more than 30 miles of trails, greenways and parks around the urban core.

Where does the LaVilla Link start and end?

The 1.3-mile LaVilla Link starts at Park and Stonewall streets in Brooklyn, crosses the Park Street Bridge, follows Lee Street and Church Street, crosses Beaver Street and ends at the S-Line Rail Trail at Wilcox and State streets, Groundwork says.

Who builds and runs the Emerald Trail?

Groundwork Jacksonville is developing the trail in partnership with the City of Jacksonville and JTA under a Memorandum of Understanding announced on October 26, 2023. City Council adopted the master plan on March 26, 2019.

Did Jacksonville lose federal money for the Emerald Trail?

Yes. A $147 million federal grant awarded on March 13, 2024, the largest one-time federal grant the City has received, was rescinded in July 2025 along with other unobligated Neighborhood Access and Equity grants, Groundwork reported. The $132 million gas tax allocation remains.

When did the Hogan Street Link start?

JTA says the groundbreaking for the Hogan Street Link, the second section of the Emerald Trail, took place in fall 2025, with construction continuing through 2026. Groundwork describes it as a 0.9-mile link from the St. Johns River to FSCJ and Springfield.

Sources

  1. Emerald Trail, MobilityWorks 2.0 projects (Jacksonville Transportation Authority) https://jtafla.com/mobilityworks-20/projects/emerald-trail/ Used for: 30 miles, 14 neighborhoods, partners, $132,000,000 estimate, council districts, Hogan Street Link groundbreaking fall 2025
  2. Groundwork Jacksonville and JTA MOU Outlines Future Development of the Emerald Trail (JTA release, October 26, 2023) https://sustainability.jtafla.com/mediacenter/media-center/press-releases/groundwork-jacksonville-and-jta-mou-outlines-future-development-of-the-emerald-trail-agreement-sets-stage-for-collaboration-and-grant-funding-opportunities/ Used for: MOU, $132M gas tax, master plan adopted March 26, 2019, segment list, roles, 40 percent status, $184M application, destination counts
  3. $147 Million-Dollar Federal Grant Awarded to the Emerald Trail (JTA release, March 13, 2024) https://jtafla.com/media-center/press-release/147-million-dollar-federal-grant-awarded-to-the-emerald-trail/ Used for: grant award, largest one-time federal grant, 132 awardees, five segments
  4. Emerald Trail (Groundwork Jacksonville) https://www.groundworkjacksonville.org/emerald-trail/ Used for: Groundwork's own project description, destination counts, master plan authors and cost, half-complete map
  5. Mayor Lenny Curry and Groundwork Jacksonville Host Groundbreaking of the Emerald Trail (Groundwork Jacksonville, August 24, 2021) https://www.groundworkjacksonville.org/mayor-lenny-curry-and-groundwork-jacksonville-host-groundbreaking-of-the-emerald-trail/ Used for: LaVilla Link groundbreaking, $8.9 million estimate, route, 14-foot width, features, designers, 2029 projection
  6. Community Celebrates the Opening of the LaVilla Link (Groundwork Jacksonville, May 6, 2024) https://www.groundworkjacksonville.org/?p=5940 Used for: opening date, funding, Model Project, connections
  7. Hogan Street Link (Groundwork Jacksonville) https://www.groundworkjacksonville.org/hogan-street-link/ Used for: 0.9 miles, route, points of interest
  8. Riverside Link (Groundwork Jacksonville) https://www.groundworkjacksonville.org/riverside-link/ Used for: 2.3 miles, FDOT path link, designers, donors, schedule as written, Memorial Park spur
  9. Hogans Creek (Groundwork Jacksonville) https://www.groundworkjacksonville.org/hogans-creek/ Used for: 2.6-mile creek, flooding, design at 60 percent, Klutho features
  10. LaVilla Link Featured in App (Groundwork Jacksonville news page) https://www.groundworkjacksonville.org/lavilla-link/ Used for: February 5, 2026 McCoys Creek Branches groundbreaking listing
  11. A Message from Kay Ehas About the $147M Grant (Groundwork Jacksonville, July 9, 2025) https://www.groundworkjacksonville.org/?p=6673 Used for: grant rescission, segments 3 and 4, 15 miles, 2031, $3.5M for Groundwork
Last updated: October 18, 2026

How this page was made

Digital Towns uses AI assistance to research and write its guides, and every page is only as good as the sources it cites. Our goal is the most accurate, useful local information possible.

This page was fact-checked twice before publishing.

If you see an error, or anything you can show is false, tell us right away and we will take a third look.