Howard Frankland Bridge in Tampa, Florida

Named for a Tampa banker and chamber president, the I-275 crossing over Old Tampa Bay opened in 1960 and has been rebuilt by FDOT with express lanes and a trail.


Short answer: The Howard Frankland Bridge carries I-275 across Old Tampa Bay between Tampa and St. Petersburg. Named for Tampa banker Howard Frankland, it opened in 1960, and a parallel span followed in 1990. FDOT opened a new southbound bridge in 2025, removed the 1960 span, and has collected SunPass tolls on the new express lanes since August 22, 2026.

Last verified: October 18, 2026, against the sources listed at the end of this page.

What is the Howard Frankland Bridge?

The Howard Frankland Bridge is the Interstate 275 crossing of Old Tampa Bay that links Tampa with St. Petersburg.

The original bridge opened in 1960 and a second, parallel span opened in 1990, according to Hillsborough County. Beginning in spring 2020 the Florida Department of Transportation built a new southbound bridge that replaced the 1960 structure and added tolled express lanes in the median and a shared-use path on the north side.

The Tampa end of the project reaches State Road 60. FDOT District Seven project page lists the limits of the rebuild as 4th Street in Pinellas County to SR 60 in Hillsborough County, a length of 5.8 miles, in the cities of St. Petersburg and Tampa. The same page gives a construction cost of $973.4 million and an estimated completion of late 2026. FDOT files the work as project 422904-2-52-01, titled I-275 (Howard Frankland Bridge) new southbound bridge between Pinellas and Hillsborough counties, with a work type of New Bridge and a phase still listed as Construction. Because the express lanes, the trail and the conversion of the older span were all delivered under that one project, the FDOT page is the main official record for the Tampa crossing.

Who was Howard Frankland?

Howard Frankland was a Tampa businessman and banker, not a public engineer, and the bridge carries his name.

Hillsborough County describes Frankland, who lived from 1901 to 1980, as a prominent Hillsborough County entrepreneur, banker and philanthropist. As proprietor of Pioneer Tire Company in Tampa he studied the properties of rubber, inventing ways to recap tires, make floor mats and produce rubber balls. He served as president of the First National Bank of Tampa and of the Greater Tampa Chamber of Commerce, and he worked to attract MacDill Air Force Base and to build a third bridge across Tampa Bay.

That third bridge was his long campaign. The county states that Frankland advocated a cross-bay span between the Gandy Bridge and the Courtney Campbell Causeway, and that he sat on the State Road Board when the Greater Tampa Chamber of Commerce suggested naming the new bridge for him. At the opening ceremony in January 1960, attended by dignitaries including Gov. LeRoy Collins, Frankland said he hoped the bridge would be a real tie of friendship linking Hillsborough and Pinellas counties, as the St. Petersburg Times reported and the county quotes.

What happened to the 1960 Howard Frankland Bridge?

The 1960 Howard Frankland Bridge has been removed, after FDOT opened a new southbound bridge in 2025 and shifted traffic onto the newer spans.

For three decades the 1960 bridge carried traffic in both directions. Hillsborough County records that it became the northbound span when a second, parallel bridge for southbound traffic opened in 1990. The county page, last modified January 30, 2024, still describes the work as a proposal FDOT was vetting for the twin-span bridge that would include express lanes, a bicycle path and accommodations for light rail, if approved; FDOT's own project page now reports the work built.

FDOT states that in 2025 it opened the new southbound I-275 bridge to traffic. The 1990s Howard Frankland Bridge, which originally connected Tampa to St. Petersburg, was converted to carry northbound traffic, while the original 1960s bridge was removed. WUSF reported in May 2026 that final work to remove the original bridge had been completed, consistent with FDOT's description.

Storm resilience was part of the design for the Old Tampa Bay crossing. In a November 2023 Tampa Bay bridge crossings resiliency overview posted by Plan Hillsborough, FDOT listed resiliency features for the new Howard Frankland Bridge, including a 6-inch concrete slab (standard and fiber reinforced), new riprap, a roadway barrier wall, a new seawall and bulkhead, flowable fill and a buried marine mattress. FDOT stated that the bridge was designed to provide 1 foot of freeboard above the anticipated wave height of a 100-year storm event. Its listed hardening measures include increasing reinforced concrete from 4 to 6 inches thick, extending the barrier along the retaining wall face, and eliminating the gap between the bulkhead cap and the barrier wall and sidewalk slab.

How do the Howard Frankland express lanes work?

The Howard Frankland express lanes are tolled lanes in the I-275 median that run from 4th Street North in St. Petersburg to just north of the bridge in Tampa.

FDOT states that the Howard Frankland express lanes are separated from the general-use lanes by barrier walls and flexible plastic poles, and that only passenger vehicles, registered vanpools and buses are allowed in the I-275 express lanes. FDOT's project factsheet repeats the same rules.

Tolling began in the summer of 2026. According to FDOT, as of August 22, 2026, tolls are being collected electronically 24 hours a day, seven days a week, on the Howard Frankland Bridge express lanes through the SunPass Prepaid Toll Program. FDOT's project page and factsheet name the payment method but do not state a per-trip amount, so this page does not list one; drivers can confirm the posted rate with FDOT before using the lanes between Tampa and St. Petersburg.

FDOT also reminds motorists of a newly posted 65 MPH speed limit across the Howard Frankland Bridge, effective August 22, 2026, with the limit reduced to 55 MPH on either side of the bridge because of active construction work zones. The contractor for the bridge project is the Archer Western and Traylor Bros joint venture.

Can people walk or bike across the Howard Frankland Bridge?

Yes, a 12-foot-wide shared-use path for pedestrians and cyclists runs along the north side of the new Howard Frankland Bridge between Tampa and St. Petersburg.

FDOT describes the path as barrier-separated and nearly seven miles long, with four shaded, sail-adorned overlooks where users can rest above Old Tampa Bay. Access is available every day from sunrise to sunset.

Access on the Tampa side is at the south end of Reo Street, with the St. Petersburg access at the north end of 4th Street. FDOT states that additional future connections from Ulmerton Road and 4th Street North in St. Petersburg, as well as Reo Street in Tampa, are being built under separate active construction projects. 83 Degrees Media, quoting FDOT, reported the same Reo Street and 4th Street access points, in an article published when the path opened.

The Tampa approach to the trail was its own project. FDOT project 447534-1-52-01 built a seawall and shared-use path along the north side of I-275 between Reo Street and the Howard Frankland Bridge, a length of 1.5 miles in Tampa and Hillsborough County. Construction began March 27, 2023, and all construction activities were completed on Friday, November 14, 2025. FDOT states that completed travel lanes will connect from the Westshore Interchange to southbound I-275 as part of that project, so the Tampa shoreline segment serves both the trail and the approach to the bridge.

What are the Howard Frankland project figures?

FDOT lists the Howard Frankland rebuild as a 5.8-mile, $973.4 million project that started in spring 2020 and is expected to be complete in late 2026.

The table below collects the figures FDOT District Seven publishes for the project that links Tampa and St. Petersburg.

Howard Frankland Bridge project details, as listed by FDOT
ItemFDOT listing
Project ID422904-2-52-01
Limits4th St (Pinellas) to SR 60 (Hillsborough)
Length5.8 miles
Project startSpring 2020
Construction cost$973.4 million
Estimated completionLate 2026
ContractorArcher Western/Traylor Bros Joint Venture
Express lane tollingElectronic, 24 hours a day, via SunPass, as of August 22, 2026
Speed limit on the bridge65 MPH, effective August 22, 2026
Reo Street seawall and trail (447534-1-52-01)1.5 miles, March 27, 2023 to November 14, 2025

Last verified: October 18, 2026, against the FDOT District Seven Howard Frankland and Reo Street project pages, the July 2026 factsheet, the Hillsborough County Faces Behind the Places entry, and the FDOT resiliency overview hosted by Plan Hillsborough.

Frequently asked questions

When did the original Howard Frankland Bridge open?

Hillsborough County dates the opening ceremony to January 1960, with Gov. LeRoy Collins among the dignitaries attending. FDOT states the original 1960s bridge was removed after the new southbound bridge opened in 2025.

How are tolls paid on the Howard Frankland express lanes?

FDOT says tolls have been collected electronically around the clock since August 22, 2026 through the SunPass Prepaid Toll Program. FDOT's project page does not list the per-trip amount.

Where does the Howard Frankland trail start in Tampa?

FDOT lists the Tampa access point at the south end of Reo Street. The St. Petersburg end connects at the north end of 4th Street. The path is open every day from sunrise to sunset.

Which vehicles can use the I-275 express lanes on the bridge?

FDOT allows only passenger vehicles, registered vanpools and buses in the express lanes. The lanes sit in the median between Tampa and St. Petersburg and are separated from the general-use lanes by barrier walls and flexible poles.

How was the new Howard Frankland Bridge designed for storms?

In a 2023 resiliency overview, FDOT said the new bridge was designed to provide 1 foot of freeboard above the anticipated wave height of a 100-year storm event, with thicker reinforced concrete, new riprap and a new seawall and bulkhead.

Sources

  1. Faces Behind the Places: Howard Frankland Bridge, Hillsborough County https://hcfl.gov/about-hillsborough/history/faces-behind-the-places/faces-behind-the-places-howard-frankland-bridge Used for: Frankland biography, naming, January 1960 opening, 1990 second span
  2. I-275 (Howard Frankland Bridge) new southbound bridge, FDOT Tampa Bay project 422904-2-52-01 https://www.fdottampabay.com/project/417/422904-2-52-01 Used for: limits, length, cost, contractor, express lanes, Aug. 22, 2026 tolls, shared-use path, Reo Street access, conversion and removal of older spans
  3. Northbound express lanes, shared-use path are open on the Howard Frankland Bridge, WUSF (May 27, 2026) https://wusf.org/text/transportation/2026-05-27/northbound-express-lanes-howard-frankland-bridge-now-open Used for: corroborates removal of the original span (with FDOT)
  4. Howard Frankland shared-use path, express toll lanes open, 83 Degrees Media (June 4, 2026) https://83degreesmedia.com/howard-frankland-shared-use-path-express-toll-lanes-open/ Used for: corroborates FDOT trail access points at Reo Street and 4th Street
  5. I-275 Howard Frankland Bridge project factsheet, FDOT District Seven (July 30, 2026) https://www.fdottampabay.com/factsheet/417?v=07302026 Used for: express lane rules and SunPass tolling
  6. Seawall and trail from Reo Street to the Howard Frankland Bridge, FDOT project 447534-1-52-01 https://www.fdottampabay.com/project/875/447534-1-52-01 Used for: Reo Street seawall and trail limits, length, dates, Westshore Interchange connection
  7. Tampa Bay Bridge Crossings Resiliency Overview, FDOT (November 2023), hosted by Plan Hillsborough https://planhillsborough.org/wp-content/uploads/2023/11/Tampa-Bay-Bridge-Crossings-Resiliency-Review-11-03-2023.pdf Used for: new bridge resiliency features and 100-year storm freeboard
Last updated: October 18, 2026

How this page was made

Digital Towns uses AI assistance to research and write its guides, and every page is only as good as the sources it cites. Our goal is the most accurate, useful local information possible.

This page was fact-checked twice before publishing.

If you see an error, or anything you can show is false, tell us right away and we will take a third look.

Report an error
Quote or describe the part that's wrong.
Explain what's actually true.
Only if you'd like a reply. Never shown publicly.

How we fact-check

Continue exploring

Photo credits