I-4 and I-275 in Tampa: What Is Being Built and When It Ends

FDOT is widening the I-4 and I-275 ramps beside Ybor City through spring 2027 and began the I-275 Westshore Interchange in January 2026.


Short answer: FDOT is improving the Downtown Tampa Interchange, where I-4 meets I-275 beside Ybor City, in a $227.5 million project expected to finish in spring 2027; it adds ramp lanes and moves the eastbound I-4 Ybor City exit to 14th/15th Streets. On I-275 at Westshore, a $653.3 million first phase began in January 2026. Downtown interchange lane closures run at night, between 9 p.m. and 6:30 a.m.

Last verified: October 15, 2026, against the sources listed at the end of this page.

Where do I-4 and I-275 meet in Tampa, and what is being rebuilt there?

I-4 and I-275 meet at the Downtown Tampa Interchange beside Ybor City, where FDOT is making safety and operational improvements in a $227.5 million project that began in fall 2023 and is expected to finish in spring 2027 (FDOT Tampa Bay).

The contractor is The Lane Construction Corporation, and the official name is the Downtown Tampa Interchange (I-275/I-4) Safety and Operational Improvements, FDOT project 445057-1-52-01. FDOT folded three project numbers, 445057-1, 445056-1 and 445056-2, into this single construction contract, so every update and closure alert for the downtown Tampa ramps is posted on one project page (FDOT Tampa Bay).

The project is a set of targeted ramp and lane fixes, not a full rebuild of the interchange. It concentrates on these downtown Tampa movements: southbound I-275 to eastbound I-4, westbound I-4 to both directions of I-275, the Ybor City exits and the I-275 exit into downtown. The project page lists two FDOT contacts for the project, 813-975-6204 for project information and 813-975-6060 for media, and lets drivers sign up for email alerts and closures (FDOT Tampa Bay).

What will change at the Downtown Tampa Interchange when it opens?

When the downtown Tampa work is finished, the busiest I-4 and I-275 ramps will gain lanes, and the eastbound I-4 exit to Ybor City will move from 21st/22nd Streets to 14th/15th Streets (FDOT Tampa Bay).

Downtown Tampa Interchange changes by movement, FDOT project 445057-1-52-01
Tampa movementBeforeAfter the project
Southbound I-275 to eastbound I-4Existing exitTwo-lane exit and a new ramp bridge on the inside of the interchange
Eastbound I-4 exit to Ybor City21st/22nd Streets14th/15th Streets
Eastbound I-4 frontage road (13th Avenue)Existing roadTwo lanes
Westbound I-4 to northbound I-275Single-lane rampTwo lanes, plus a merge lane on northbound I-275 to the Dr. Martin Luther King Jr. exit
Westbound I-4 to southbound I-275Two-lane rampThree lanes
Southbound I-275 between Palm Avenue and Jefferson StreetExisting shouldersWider shoulders; downtown exit shifted west

Every entry in the table comes from FDOT's description of the downtown interchange improvements (FDOT Tampa Bay). For eastbound drivers bound for Ybor City, the exit moves west to 14th/15th Streets, so they will leave I-4 before reaching the old 21st/22nd Streets exit.

The merge lane on northbound I-275 is built to the west of the current alignment, between I-4 and the Dr. Martin Luther King Jr. exit, and the southbound I-275 exit into downtown Tampa also shifts west (FDOT Tampa Bay). Those two changes pair with the lanes FDOT already added north of downtown in 2025, described below.

How far along is the Downtown Tampa Interchange work in 2026?

By August 2026, FDOT reported the steel girders over Nebraska Avenue, the pavement for the new Ybor City exit from northbound I-275 and the bridge decks over Palm Avenue all 100% complete (FDOT Tampa Bay).

The same August 2026 report lists 96% of utilities relocated, 91% of old storm drainage pipes removed, 89% of new major drainage pipes installed, 85% of the mechanically stabilized earth walls built and 85% of the new Intelligent Transportation Systems fiber installed, with lighting and signals at 14th and 15th Streets in progress (FDOT Tampa Bay). The items still short of 100% in that report are utilities, drainage, walls, fiber and the 14th and 15th Streets lighting and signals.

Lane closures for the downtown interchange are scheduled at night between 9 p.m. and 6:30 a.m., and interstate ramps may occasionally close between 11 p.m. and 5 a.m. (FDOT Tampa Bay). Heavy machinery works day and night, and FDOT warns of noise, vibration and bright lights after dark, which matters to residents living next to the ramps.

For a late-night trip through the interchange, the practical step is to check before leaving. FL511, Florida's official source for real-time traffic information, lists traffic incidents, cameras, message signs and construction information for the Tampa Bay region (FL511), and the FDOT project page posts closures and takes email sign-ups for alerts (FDOT Tampa Bay).

What is being built on I-275 at Westshore?

On I-275 at Westshore, FDOT began rebuilding the I-275/SR 60 interchange in January 2026, starting with a $653.3 million Phase I contract held by Superior-Lane Joint Venture (FDOT Tampa Bay).

The construction limits run along I-275 from the Howard Frankland Bridge to east of Lois Avenue and along SR 60 from I-275 to north of Spruce Street. FDOT is delivering the job as a phased design-build, and the first phase, called Priority 1A, is under way (FDOT Tampa Bay).

Priority 1A builds northbound I-275 Express Lanes from the Howard Frankland Bridge to a future Reo Street Bridge, replaces the loop ramp from eastbound SR 60 to northbound I-275 with a flyover, and adds a flyover from the Howard Frankland Bridge to SR 60 and Tampa International Airport. It also adds a southbound I-275 entrance ramp from Reo Street and reconnects local streets at Reo Street, Occident Street and Trask Street under the interstate, with shared-use paths for walking and cycling (FDOT Tampa Bay).

Westshore drivers should expect a long job. FDOT says the future phases of the Westshore Interchange are scheduled for funding in 2030 and 2032 (FDOT Tampa Bay), so the full interchange will not be finished with Phase I. The project information line listed by FDOT is 813-975-3691.

Which I-275 projects near Tampa are already finished or opening?

The I-275 widening from north of I-4 to north of Hillsborough Avenue was finished on March 5, 2025, and the new Howard Frankland Bridge express lanes are open, with tolling since August 22, 2026 (FDOT Tampa Bay; FDOT Tampa Bay).

The completed I-275 job north of downtown Tampa covered 2.5 miles and cost $96.7 million. It added one lane in each direction within the existing right-of-way, built noise barrier walls, installed fencing and Intelligent Transportation System devices, and rebuilt the overpasses between Floribraska Avenue and Hillsborough Avenue (FDOT Tampa Bay). FDOT's project page now states that the project has been completed and keeps its information archived for reference (FDOT Tampa Bay).

West of Westshore, the Howard Frankland Bridge replacement carries I-275 across Old Tampa Bay. FDOT has opened new express lanes in the I-275 median from 4th Street North in St. Petersburg to just north of the bridge in Tampa; tolls are collected electronically 24 hours a day through the SunPass Prepaid Toll Program, and only passenger vehicles, registered vanpools and buses may use the lanes (FDOT Tampa Bay). The $973.4 million project lists late 2026 for completion, and a 12-foot-wide, barrier-separated shared-use path has opened along the north side of the bridge (FDOT Tampa Bay).

FDOT called the Howard Frankland Bridge replacement the largest transportation project ever delivered in its District 7; the new bridge opened to traffic in summer 2025 and, as built, increased capacity by 50% (FDOT news release, August 27, 2025). The same release announced the groundbreaking of the I-275 expansion on the Pinellas County side, which adds express lanes that flow into the bridge, while on the Tampa side the Westshore Interchange work continues, with its later phases scheduled for funding in 2030 and 2032.

How does I-4 connect to the Port of Tampa and the Selmon Expressway?

Eastbound from downtown Tampa, I-4 links to the Selmon Expressway and the Port of Tampa through the I-4/Selmon Expressway Connector, a $421 million toll connector whose ribbon was cut on December 28, 2013 (Federal Highway Administration).

The connector used $222 million in federal-aid funding, including $105 million in American Recovery and Reinvestment Act dollars. FHWA described it as a series of north-south toll ramps to and from I-4, the Selmon Expressway and 20th Street, providing a truck-only direct access route to the Port of Tampa and removing truck traffic from downtown Ybor City (FHWA).

The same release names the connector as an evacuation route for area residents in a hurricane and as an alternative route for commuters into downtown Tampa (FHWA). For Tampa drivers, that means a crash or closure on the downtown I-4 ramps leaves a tolled alternative route into downtown Tampa, and FL511 shows which route is moving before a trip (FL511).

Frequently asked questions

When will the I-4 and I-275 interchange construction in Tampa be finished?

FDOT expects the Downtown Tampa Interchange project to finish in spring 2027. Work began in fall 2023 under a $227.5 million contract with The Lane Construction Corporation, and the August 2026 update showed the Nebraska Avenue girders and Palm Avenue bridge decks complete.

Where is the new Ybor City exit from I-4?

The eastbound I-4 exit to Ybor City is being moved from 21st and 22nd Streets to 14th and 15th Streets as part of the Downtown Tampa Interchange project, and FDOT reported lighting and signal work at 14th and 15th Streets under way in August 2026.

When are lanes closed on I-275 and I-4 in downtown Tampa?

FDOT schedules lane closures for the Downtown Tampa Interchange at night between 9 p.m. and 6:30 a.m., and interstate ramps may close between 11 p.m. and 5 a.m. Current closures are posted on the FDOT project page and on FL511.

What is FDOT building at the Westshore Interchange in Tampa?

Phase I of the I-275/SR 60 Westshore Interchange, started in January 2026 for $653.3 million, adds northbound I-275 Express Lanes, a flyover from the Howard Frankland Bridge to SR 60 and Tampa International Airport, a flyover replacing the eastbound SR 60 to northbound I-275 loop ramp, a Reo Street entrance ramp and reconnected streets at Reo, Occident and Trask.

Do the Howard Frankland Bridge express lanes charge tolls?

Yes. As of August 22, 2026, FDOT collects tolls electronically 24 hours a day on the I-275 express lanes across the Howard Frankland Bridge through the SunPass Prepaid Toll Program. Only passenger vehicles, registered vanpools and buses may use them.

Sources

  1. Downtown Tampa Interchange (I-275/I-4) Safety and Operational Improvements, FDOT Tampa Bay https://fdottampabay.com/project/839/445057-1-52-01 Used for: start, cost, completion, contractor, ramp-by-ramp scope, Ybor City exit relocation, night closure windows, August 2026 progress, combined project numbers, contacts
  2. Westshore Interchange (I-275/SR 60), FDOT Tampa Bay https://www.fdottampabay.com/project/967/447107-2-32-447107-2-52-447107-3-52-447107-4-52 Used for: limits, January 2026 start, $653.3 million Phase I cost, contractor, Priority 1A scope, future phase funding years
  3. I-275 Capacity Improvements from north of I-4 to north Hillsborough Avenue, FDOT Tampa Bay https://fdottampabay.com/project/706/431821-2-52-01 Used for: completion on March 5, 2025, 2.5-mile length, $96.7 million cost, added lanes and overpass reconstruction
  4. Howard Frankland Bridge replacement, FDOT Tampa Bay https://www.fdottampabay.com/project/417/422904-2-52-01 Used for: I-275 express lanes, tolling since August 22, 2026, SunPass Prepaid, eligible vehicles, cost and completion
  5. Federal Highway Deputy Administrator Nadeau Joins in Ribbon Cutting for I-4 Connector, FHWA, December 28, 2013 https://highways.fhwa.dot.gov/newsroom/federal-highway-deputy-administrator-nadeau-joins-ribbon-cutting-i-4-connector Used for: I-4/Selmon Expressway Connector opening, cost and federal share, port truck access, Ybor City truck relief, evacuation route
  6. Governor Announces Major Infrastructure Investments for Tampa Bay, FDOT news release, August 27, 2025 https://www.fdot.gov/info/co/news/2025/08272025 Used for: Howard Frankland Bridge opening, 50% capacity increase, largest District 7 project, I-275 Pinellas expansion groundbreaking
  7. FL511, Florida's official source for real-time traffic information https://fl511.com Used for: real-time traffic, cameras, construction and emergency information
Last updated: October 15, 2026

How this page was made

Digital Towns uses AI assistance to research and write its guides, and every page is only as good as the sources it cites. Our goal is the most accurate, useful local information possible.

This page was fact-checked twice before publishing.

If you see an error, or anything you can show is false, tell us right away and we will take a third look.

Report an error
Quote or describe the part that's wrong.
Explain what's actually true.
Only if you'd like a reply. Never shown publicly.

How we fact-check

Continue exploring

Photo credits