Short answer: Big Blue is the former City of Vero Beach electric power plant at 100 17th Street, on the Indian River Lagoon at the foot of the Alma Lee Loy Bridge. The city planned it in 1958 as a steam electric plant to replace its downtown diesel plant and shut it down in December 2015 under an agreement with the Orlando Utilities Commission. The building still stands on city land now planned for the Three Corners waterfront project.
Last verified: October 16, 2026, against the sources listed at the end of this page.
What was Vero Beach's Big Blue power plant?
Big Blue is the name the City of Vero Beach uses for its decommissioned electric power plant, the large industrial building on the Indian River Lagoon north of the Alma Lee Loy Bridge in Indian River County.
The city's power plant property overview places the plant at 100 17th Street and measures the power plant property at 20.92 acres, noting that the boundary contains submerged lands owned by the City of Vero Beach. The city's 2023 offering memorandum for Three Corners describes it as the former electric power plant property next to the Indian River Lagoon and says the parcel is still occupied by the structures that defined its historical use: large industrial buildings, with zoning that still reflects the industrial nature of the property.
The plant was the second home of a city electric system that began almost a century earlier. The National Register of Historic Places nomination for the Vero Beach Diesel Power Plant records that in 1919 the new town of Vero began planning for its own electrical services, a decision it calls one with long range effects on the development of the community.
Why did Vero Beach build its own power plant?
Vero Beach ran its own power plants because the town bought out a failing private utility in its first year.
According to the National Park Service nomination, a small private plant furnished electric power on a limited basis when Vero was incorporated in 1919. Its entire generating unit consisted of two 25 HP engines that generated electricity only on certain days and for short periods of time. When growth overwhelmed the private company, it offered the town the electrical plant for $9,000, and the town council purchased it when Vero was only a year old.
The town then built the Vero Beach Diesel Power Plant in 1926, which the nomination calls the first public utilities facility built by the town and the oldest municipal building in the community. By 1958 the population of Vero Beach had grown from 800 in 1920 to over 8,700, the city decided the diesel plant had reached its capacity, and plans were made to build a new steam electric power plant on the Indian River. The nomination also links the city's utilities to growth: in 1957, municipal services which by then included electricity, water and sewer attracted yet another industry, as the Piper Aircraft Company purchased airport grounds and built new buildings for a growing small airplane industry. That riverfront plant is the building now called Big Blue. The old diesel plant was kept as backup, and the nomination notes that several times after the new power plant went on line, the diesel units were called upon to provide start up electricity after regional power blackouts.
Why did Vero Beach shut Big Blue down?
Vero Beach shut Big Blue down in December 2015 as part of its agreement with the Orlando Utilities Commission, according to the city.
The City of Vero Beach offering memorandum states that as part of its agreement with the Orlando Utilities Commission, the City shut down its electric power plant in December 2015. The city later left the electric business entirely. Florida Power and Light reported that it completed the purchase of the City of Vero Beach's electric utility on December 17, 2018, welcoming approximately 35,000 new customers after nearly a decade of work.
In the same release, FPL said the Vero Beach City Council had approved a $185 million agreement that allowed the city to exit its contractual obligations, pay off its existing debt and receive a cash payment. FPL also stated that its typical 1,000-kWh customer bill was about 20 percent lower than rates charged by Vero Beach at the time. The city Three Corners page ranks the future use of the waterfront as second in importance only to the recent sale of the municipal power plant.
Is the Big Blue building still standing?
The main Big Blue building has not been demolished; the city's own 2023 marketing document describes the industrial buildings as still standing.
The Vero Beach offering memorandum says the existing power plant structure is a nonconforming use under the City's Comprehensive Plan. It also says the City has agreed to lease a portion of the site to FPL to relocate the electric substation from the Electric Power Plant Property, a step tied to clearing the parcel for new uses.
The Vero Beach document leaves open how much of the building survives. It says development could reuse either the entire existing structure or only a portion, with indoor spaces focused on reuse of the great hall. It notes that a rooftop bar or restaurant in Big Blue, at a height of 60 ft. above street level, would offer unique views of the lagoon, while any new structure that does not make use of Big Blue would have to comply with the current maximum 65-foot building height limitation.
Big Blue sits on one of three city owned parcels that make up the Three Corners site in Vero Beach. The memorandum puts the total at 33.7 acres with 1,300 feet of waterfront along the Indian River Lagoon, at the intersection of 17th Street and Indian River Boulevard. The water treatment plant parcel to the south occupies another 16.3 acres, and a vacant postal annex occupies 4.6 acres across Indian River Boulevard. The memorandum says a new wastewater plant was under design to relocate that facility to the city's airport, and that the current facility would be decommissioned within five years.
How did the city decide Big Blue's future?
The city opened Big Blue to the public in 2020 while it decided whether to keep, reuse or replace it.
The Three Corners Master Concept page says the city selected the design firm DPZ CoDesign to run a community engagement process, and that the project began on November 19, 2019, with a presentation to City Council and the formation of the Three Corners Steering Committee. Residents submitted ideas through speakupverobeach.com, and the outreach culminated in a week long design charrette at the Vero Beach Community Center.
The Vero Beach project timeline lists power plant tours on January 18 from 10am to noon and January 25 from 1pm to 3pm, open to the public with no registration necessary, followed by charrette week from January 27 to 31, 2020, with Andres Duany and DPZ CoDESIGN. DPZ prepared five scenarios for the site, including mothballing it, cultural and recreational use, and maximum development, and the Steering Committee reviewed them on February 25, 2020. The City Council adopted the master concept plan on February 1, 2022.
What is planned for the Big Blue site?
The Big Blue site is planned as a public waterfront destination with a hotel, park and commercial space under a master developer still in negotiation with the city.
The former power plant site is one of the city owned properties listed in Section 5.05 of the Vero Beach City Charter, which requires voter approval for a sale or lease. The city reports that on November 8, 2022, voters approved by 79% a charter provision allowing the site to be leased for restaurant, retail, hotel or similar commercial uses, while keeping public access to the waterfront, recreational space and pedestrian promenades, with all uses open to the public.
The council adopted a Comprehensive Plan amendment for the site on February 27, 2024 (Ordinance 2024-03) and the Three Corners Waterfront District regulations on August 12, 2025 (Ordinance 2025-08). After a reissued request for proposals drew two responses on December 17, 2024, the council selected Clearpath Services of Bloomington, Indiana, as preferred developer on April 22, 2025. As of the city page checked on October 15, 2026, staff had been directed to negotiate a master development agreement with a new entity that adds Madison Marquette, and to bring it back to the council for approval.
The Vero Beach selection followed several rounds. In 2022 the city requested information from interested developers and received responses from Don Urgo, E2L Real Estate and Equity First. In 2025 an evaluation committee of two city staff and three advisory board members ranked the two proposals on March 4, with analysis by PFM Financial Advisors and Stantec, and interviewed both firms on March 31. On May 6, 2025, the city gave Clearpath 90 days to document its financial capacity to complete the project. Separately, the council approved a lease with the Youth Sailing Foundation on August 8, 2023, for sailing facilities on the wastewater plant site.
| Date | Event | Source |
|---|---|---|
| 1919 | Vero begins planning its own electric service | National Park Service |
| 1926 | Downtown diesel power plant built | National Park Service |
| 1958 | City plans a steam electric plant on the Indian River | National Park Service |
| December 2015 | Plant shut down under the Orlando Utilities Commission agreement | City of Vero Beach |
| December 17, 2018 | FPL completes purchase of the city electric utility | FPL |
| November 8, 2022 | Voters approve commercial leasing of the site | City of Vero Beach |
| April 22, 2025 | Council selects Clearpath Services | City of Vero Beach |
Last verified: October 15, 2026, against the National Park Service nomination, FPL's December 2018 release and four City of Vero Beach pages and documents on the power plant and Three Corners.
Frequently asked questions
Where is the Big Blue power plant in Vero Beach?
At 100 17th Street, on the Indian River Lagoon north of the Alma Lee Loy Bridge. The city charter describes the site as west of the Indian River and east of Indian River Boulevard, part of the Three Corners waterfront.
When did Big Blue stop producing electricity?
The City of Vero Beach says it shut the plant down in December 2015 as part of its agreement with the Orlando Utilities Commission. FPL bought the city's electric utility three years later, on December 17, 2018.
Has Big Blue been demolished?
No. The city's 2023 offering memorandum says the parcel is still occupied by large industrial buildings, and it invites developers to reuse all or part of the structure, with a focus on the great hall.
How tall is Big Blue?
The city describes a possible rooftop restaurant at a height of 60 ft. above street level. Any new building that does not reuse Big Blue would have to meet the current maximum 65-foot building height limitation.
How big is the Big Blue site?
The city's power plant property overview gives 20.92 acres. City documents give different totals for the wider Three Corners site: 33.7 acres in the 2023 offering memorandum and 38 acres on the master concept page.
Sources
- Three Corners Master Concept (City of Vero Beach) https://www.covb.org/504/Three-Corners-Master-Concept Used for: DPZ, November 19, 2019 start, 2022 referendum, ordinances, RFI responders, evaluation, Clearpath selection and negotiation status, Youth Sailing lease
- Three Corners Project Timeline (City of Vero Beach) https://www.covb.org/545 Used for: January 2020 tours and charrette
- National Register of Historic Places nomination, Vero Beach Diesel Power Plant (National Park Service) https://npgallery.nps.gov/GetAsset/94e03588-2ca4-4f43-bae1-6fde38e7966e Used for: 1919 planning, $9,000 purchase, 1926 diesel plant, 1958 steam plant decision, Piper
- Three Corners Waterfront Development Site offering memorandum (City of Vero Beach, 2023) https://www.covb.org/DocumentCenter/View/7157/Vero-Beach-Three-Corners-OM-FINAL-9-22-23-compressed-PDF Used for: December 2015 shutdown, nonconforming use, substation lease, 60 ft rooftop, 65-foot limit, 33.7 acres, parcel sizes, wastewater plant relocation
- Power Plant property overview, August 2021 (City of Vero Beach) https://www.covb.org/DocumentCenter/View/7159/Power-Plant-Overview-Aug-2021-11X17-PDF Used for: 100 17th Street address and 20.92 acres
- FPL welcomes 35,000 new customers from the City of Vero Beach electric system (FPL, December 17, 2018) https://newsroom.fpl.com/2018-12-17-FPL-welcomes-35-000-new-customers-from-the-City-of-Vero-Beach-electric-system Used for: December 17, 2018 purchase, 35,000 customers, $185 million agreement
How this page was made
Digital Towns uses AI assistance to research and write its guides, and every page is only as good as the sources it cites. Our goal is the most accurate, useful local information possible.
This page was fact-checked twice before publishing.
If you see an error, or anything you can show is false, tell us right away and we will take a third look.
Report an error
Thank you. We'll take a third look and correct the page if it's wrong.